The grand opening of the latest float line took place on 08/05/2019 in Ujazd (Poland). Production is already running at full capacity, barely three months after ignition of the new melting furnace.
The project's construction schedule was very ambitious in its planning and implementation. This enabled the furnace to be lit just 51 weeks after the ground-breaking ceremony. The experienced project team even managed to reduce the construction period by two months compared to the previous tank.
The new furnace is named "Gabriela". This follows the tradition that each Euroglas furnace bears its patron's first name. In this case the daughter of Managing Director Piotr Noga.
The additional capacity enables Euroglas Polska to satisfy increased demand in the Polish and European glass market.
22.07.2019, EuroGlas
Should the content or the design of these sites violate third parties rights or legal prescriptions, we kindly ask you to send us a respective message without invoice or cost. We guarantee that passages where the claim is considered as justified will be removed immediately, without any necessity to involve any lawyer into this issue. We will reject any claim caused by submission of a honorary note in this regard without any prior contact and confirmation of the issueby us and we reserve the right ssue counter claim ourselves because of violation of aforesaid conditions.