As part of the general repair of furnace 4, the furnace drain took place at the Noelle + von Campe plant in Boffzen on April 29, 2025.
Glass melting technology specialist HORN is equipping the repaired environmentally friendly furnace 4 with the latest, low-emission technology and is responsible for the complete detailed planning of the refractories as well as the steel construction for the furnace, distributor and five forehearths.
In this project, HORN experts are carrying out the furnace drain, demolition, the complete construction work for the refractory material, steel and equipment as well as the heating up.
The new regenerative end fired furnace is expected to be commissioned in July 2025.
20.05.2025, HORN Glass
Should the content or the design of these sites violate third parties rights or legal prescriptions, we kindly ask you to send us a respective message without invoice or cost. We guarantee that passages where the claim is considered as justified will be removed immediately, without any necessity to involve any lawyer into this issue. We will reject any claim caused by submission of a honorary note in this regard without any prior contact and confirmation of the issueby us and we reserve the right ssue counter claim ourselves because of violation of aforesaid conditions.