The construction site in Shehong city is currently in full swing. After having finished with the steel construction, HORN has started with the supervision of the refractory construction.
Having started with the steel construction at the beginning of January 2025, Sichuan Skyhorse Glass Co., Ltd. will soon be equipped with a new state-of-the-art, energy-efficient end fired glass melting furnace with six production lines for the production of container glass.
Under the construction supervision of HORN together with its subsidiary company HORN Glass Technology (Beijing) Co., the new furnace will be commissioned in Q3 2025.
For more information about the project:
02.07.2025, Horn Glass Industries
Should the content or the design of these sites violate third parties rights or legal prescriptions, we kindly ask you to send us a respective message without invoice or cost. We guarantee that passages where the claim is considered as justified will be removed immediately, without any necessity to involve any lawyer into this issue. We will reject any claim caused by submission of a honorary note in this regard without any prior contact and confirmation of the issueby us and we reserve the right ssue counter claim ourselves because of violation of aforesaid conditions.